Create a milestone trigger
Create a
milestone trigger using an
escalation map or an alert task.
Use an escalation map
Use an escalation map to create a specific job to deal with the milestone trigger.
- In the New milestone dialog box, click the Triggers tab.
- Click
- On the Process list, select a process to use as an escalation process that will take some corrective action.
-
To set the trigger to execute later than or before the milestone due date, set the
Target duration in days, hours, minutes, and/or seconds and then select
After or
Before. For example, to execute the trigger three days before the milestone
is due, set 3 days for the target duration and select Before.
To execute the trigger when the milestone due date is met, keep the target duration value 0.
- Click Add.
Create an alert
Create an alert task using milestones to appear on the work queue of the selected resource to notify escalations.
- In the New milestone dialog box, click the Alerts tab.
- Click .
- See Create an alert for more information.